Chronology of Vienna Metro Planning
From the Office of Supervisor Linda Smyth
Fairfax County Board of Supervisors

The most recent planning efforts and rezoning application review of the south side of the Vienna Metro transit station area has occurred over a nearly four year period. The review of the rezoning application has been ongoing for nearly a year.

Comprehensive Plan Changes

Issues of Concern identified During Planning Efforts

Metro Capacity

Replacement of Metro Parking

Transportation – TDM’s

School Capacity

Environmental Issues

Mix of Uses

Protection of Stable Neighborhoods

The Rezoning Application RZ/FDP 2003-PR-022

After approval of the Comprehensive Plan changes Supervisor Smyth encouraged and anticipated continued citizen participation in the rezoning process. She specifically identifying an expectation that the developer will need to listen to and work closely with the community through the next steps of the process.


Partial List of Meetings residents participated in
since the submission of the rezoning application

3/14/05 Meeting with Supervisor Smyth, including Planning Staff, Sierra Club, Coalition for Smarter Growth and Fair Growth.
3/22/05 TDM Advisory Team Meeting (The TDM Advisory Team included County Staff , Providence Supervisor’s Office representatives, the applicant, Commissioner Lawrence, the TDM Consultant Urban Trans and representatives from the community including Fair Growth.)
3/30/05 TDM Advisory Team Meeting
3/31/05 Fair Growth representatives meeting with Supervisor Smyth & Planning and FDOT Staff
4/7/05 TDM Advisory Team Meeting
4/18/05 TDM Consultant Survey group meeting – included HOA representatives adjacent to the Vienna Metro
4/21/05 TDM Advisory Team Meeting
5/2/05 First Land Use Seminar UrbanTrans Consultants, the transportation demand management (TDM) consultant for the Vienna Metro Station Area, presented an overview of the project process and gather community feedback / suggestions for the project.
5/12/05 TDM Advisory Team Meeting
5/24/05 TDM Advisory Team Meeting
5/25/05 Survey group meeting- included HOA/ Civic organizations representatives adjacent to the Vienna Metro
6/1/05 Public meeting held at Marshall Rd. School
6/9/05 TDM Advisory Team Meeting
6/15/05 TDM Advisory Team Meeting
6/21/05 4th Land Use Seminar – attended by TDM Consultant to report on findings and gather additional feedback regarding draft TDM Program report
6/29/05 TDM Meeting
7/12/05 WMATA Vienna Metro Station Community Outreach Meeting at Oakton H.S.
9/15/05 Fair Growth representatives meeting with Supervisor Smyth and Commissioner Lawrence
10/25/05 Fair Growth representatives meeting with applicant’s new TDM consultant, the applicant and county planning and FDOT staff.

 

Back to MetroWest Alert